Road & Sidewalk Construction Projects
Road & Sidewalk Projects
Roads & Sidewalks to be Improved |
Description |
Estimated Start* |
---|---|---|
Howard St. Rand St. McLeavey St. Oxford St. Winthrop Ave. |
D&R Paving will be paving the roads. | November 4, 2024 |
670 Washington Ave. - 810 Washington Ave. | J Marchese & Sons will be repairing sidewalks and the roadway in the area. | September 1, 2024 - October 31, 2024 |
Campbell Ave. & North Shore Rd. Public Stairs | The public stairs linking Campbell Ave. and North Shore Road will be closed for reconstruction. | May 6, 2024 |
*estimated dates are subject to change due to weather and paving company's availability. Paving to follow approximately 2-4 weeks after the roadway is milled.
Water/Sewer Projects
Area Impacted | Project Explanation | Timeline |
---|---|---|
Derby St. Grover St. |
Revere Water & Sewer Department will be working at the intersection of Derby Rd. and Grover St. We will be replacing three existing water gate valves and adding a fourth to improve our water system's reliability and minimize the impact of any future disruptions. Residents in the affected area will receive notifications, and any water service interruptions will be brief. |
October 22, 2024 - October 25, 2024 |
Billows Ave. Broadsound Ave. |
Sean Farrell Excavation will be working on water infrastructure in the area starting October 7th, from 8:00 A.M. to 5:00 P.M. This project is expected to take approximately one month to complete. Please note that some residents may experience temporary interruptions to their water service during this time. Those affected have already been informed about the specifics of the service interruption. We anticipate that water services will be restored promptly upon completion of the work, and there is a possibility that water may be turned back on earlier than expected. While some residents receiving this notification may not be directly impacted, we wanted to ensure everyone is informed about the ongoing work in the area. |
October 7, 2024 - November 8, 2024 |
City Wide |
10A Storm water extensions The program aims to eliminate sump pumps from the sewer system and upgrade the storm water system. |
|
|
Liberty Ave Drainage Extension |
|
City Wide Hydrant and Valve Replacement Program |
Replacement of various aging hydrants and gate valves located throughout the city. |
|
|
Watermain Replacement Project to update aging infrastructure on North Shore Rd for better water quality and more reliable distribution system. This project has be split into two phases: Phase one will be completed first and will include North Shore Rd. from Revere St. to Shawmut St. Phase two will continue in the Spring of 2025 and continue on North Shore Rd. from Shawmut St. down to 151 VFW Parkway (Wonderland Shopping Center) North Shore Rd. entrance |
|
Traffic Alerts
Area Impacted |
Project Explanation |
Timeline |
---|---|---|
Fernwood Ave. Allston St.
|
National Grid and RJ Devereaux will be performing infrastructure upgrades in the area of 84 to 125 Fernwood Ave.; 14 to 60 Allston St. As part of this project, National Grid will also replace the natural gas service piping that connects the main to the customer’s gas meters. Construction hours and days: 7:00 a.m. – 4:00 p.m. Monday through Saturday. If you have any questions about this project please contact National Grid @781-663-3120 |
September 3, 2024 - November 26, 2024 |