Road Work and Construction Projects

The City of Revere is committed to completing its roadway improvement program in a professional, comprehensive and transparent manner. Below, view a list of current and upcoming roadway and drainage infrastructure improvement projects. For road projects under the city's roadway improvement program, Mayor Arrigo asked the Engineering and Economic Development departments to conduct a comprehensive study of wear and tear on city streets.

2019 Road Construction Projects

This is not the comprehensive list of 2019 projects. We will update this page with ongoing information about roads to be worked on into the Summer.

Also note that this is just the work that the City is taking care of, and does not include work from National Grid or other outside entities. 

All dates are tentative, contingent on weather.

For more information about ongoing projects, contact Revere 311.

Road to be Improved Project Explanation Expected Start Paving Date
Tuckerman St. Granite Curb, Sidewalk Reconstruction, Milling, Paving Sidewalk: Week of July 22
Road: Week of July 29
Weeks of Aug 12 /
Aug 19
True St Sidewalk Reconstruction, Milling, Paving Sidewalk: Week of July 8 Road: Week of July 29 Weeks of Aug 12 /
Aug 19
Prospect Ave. Milling and Paving Week of July 29 Weeks of Aug 12 /
Aug 19
Charger (Near DPW Yard and Gym) Milling and Paving May 24 Complete
Pitcairn Milling and Paving May 23-24 Complete
Conant Milling and Paving May 23 Complete
Augustus Milling and Paving May 22-23 Complete
Pemberton Milling and Paving May 22 Complete
Crescent Ave. - Winthrop Ave to Winthrop Pkwy Grinding, Repairs, Repave
Sidewalk curb work between Summer and Winthrop
Week of April 2, 2019 Complete
Curtis Rd. Grinding, Repairs, Repave Week of April 2, 2019 Complete
Garfield Ave. (Blake to Centennial) Grinding, Repairs, Repave Week of April 2, 2019 Complete
Fitzhenry Sq. Area Grinding, Repairs, Repave Week of April 2, 2019 Complete
Nahant Ave. Grinding, Repairs, Repave Week of April 2, 2019 Complete
Kimball Ave. Grinding, Repairs, Repave Week of April 2, 2019 Complete
Calumet St. Repairs, Asphalt overlay Week of April 9, 2019 Complete
Bay Rd. Grinding, Repairs, Repave Week of April 9, 2019 Complete
McKinley St. Grinding, Repairs, Repave Week of April 9, 2019 Complete
Mountain Ave. (Dedham to Broadway) Grinding, Repairs, Repave Week of April 9, 2019 Complete
Kingman Ave. Grinding, Repairs, Repave Week of April 9, 2019 Complete
Dedham St. Grinding, Repairs, Repave Week of April 9, 2019 Complete
Senior Center parking lot Reconstruction, paving April 25 to May 10 Complete