Road Work and Construction Projects

The City of Revere is committed to completing its roadway improvement program in a professional, comprehensive and transparent manner. Below, view a list of current and upcoming roadway and drainage infrastructure improvement projects. For road projects under the city's roadway improvement program, Mayor Arrigo asked the Engineering and Economic Development departments to conduct a comprehensive study of wear and tear on city streets.

The following are the 2019 Road Construction Projects. We will update this information as it is provided.

This is not the comprehensive list of 2019 projects. We will update this page with ongoing information about roads to be worked on into the Summer.

Also note that this is just the work that the City is taking care of, and does not include work from National Grid or other outside entities. 

All dates are tentative, contingent on weather.

Updated May 20, 2019

Road to be Improved Project Explanation Expected Start Completion Time Paving Date
Charger (Near DPW Yard and Gym) Milling May 24 1-2 days Weeks of June 10 or 17
Pitcairn Milling May 23-24 1-2 days Weeks of June 10 or 17
Conant Milling May 23 1-2 days Weeks of June 10 or 17
Augustus Milling May 22-23 1-2 days Weeks of June 10 or 17
Pemberton Milling May 22 1-2 days Weeks of June 10 or 17
Crescent Ave. - Winthrop Ave to Winthrop Pkwy Grinding, Repairs, Repave
Sidewalk curb work between Summer and Winthrop
Week of April 2, 2019 4-5 Weeks Complete
Curtis Rd. Grinding, Repairs, Repave Week of April 2, 2019 4-5 Weeks Complete
Garfield Ave. (Blake to Centennial) Grinding, Repairs, Repave Week of April 2, 2019 4-5 Weeks Complete
Fitzhenry Sq. Area Grinding, Repairs, Repave Week of April 2, 2019 4-5 Weeks Complete
Nahant Ave. Grinding, Repairs, Repave Week of April 2, 2019 4-5 Weeks Complete
Kimball Ave. Grinding, Repairs, Repave Week of April 2, 2019 4-5 Weeks Complete
Calumet St. Repairs, Asphalt overlay Week of April 9, 2019 4-5 Weeks Complete
Bay Rd. Grinding, Repairs, Repave Week of April 9, 2019 4-5 Weeks Complete
McKinley St. Grinding, Repairs, Repave Week of April 9, 2019 4-5 Weeks Complete
Mountain Ave. (Dedham to Broadway) Grinding, Repairs, Repave Week of April 9, 2019 4-5 Weeks Complete
Kingman Ave. Grinding, Repairs, Repave Week of April 9, 2019 4-5 Weeks Complete
Dedham St. Grinding, Repairs, Repave Week of April 9, 2019 4-5 Weeks Complete
Senior Center parking lot Reconstruction, paving April 25 to May 10 2 weeks To be Completed Shortly