Update on Broadway road work: Milling of Broadway from Mountain Ave to Revere St scheduled for July 16-18

June 30, 2017

The trenching in the street required to power the new street lights on Broadway is now complete. National Grid electrical work is being completed to prepare for the delivery of new street lights.

Milling of the roadway from Mountain Ave. to Revere St is scheduled for Sunday night July 16th into July 17th, continuing Monday night into Tuesday if necessary.

The paving preparation crew is scheduled to follow behind the milling operation that same week.

The plan is to pave approximately two weeks after milling is completed - so ideally, around the first week of August. Of course, this is all subject to weather and other possible delays; we will keep residents updated as new information becomes available.

If all goes according to the current schedule, the road should be paved and all the lights installed and powered up by early to mid August.

Thank you to all residents and businesses for your patience during this roadwork.

Back to News

Mayor's Office
Contact Information
Patrick M. Keefe Jr.
Mayor
Linda DeMaio
Executive Secretary/Schedule
781-286-8111
Claudia Correa
Chief of Staff
781-286-8111
Robert Marra
Senior Advisor to the Mayor
781-286-8111
Follow us on Social Media!
Facebook Twitter Instagram
Feedback
Provide Website Feedback

There was a problem with your submission. Please correct the issues below

* Required Fields

Please wait…