Over the past 15 years, a half billion dollars in public and private investment has transformed Revere Beach. There has been a rebirth of the oceanfront as a public recreational area and as a quality place to live and work; and more is yet to come. Among the major investments already in place or soon to begin:

• nearly $5 million to restore and recreate the reservation’s pavilions, bandstand, police station and period lighting in historically accurate fashion

ren2.JPG (14221 bytes)• a $6 million beach re-nourishment, re-sanding and widening project by the U.S. Army corps of Engineers

• nearly $45 million was expended to upgrade the MBTA Blue Line including a total reconstruction of the Revere Beach and Wonderland Stations

ren1.GIF (25825 bytes)• the development of the $10 million, 80,000 square foot office building at 300 Ocean Avenue

• the development of over 1100 rental and condominium units in 10 mid and high rise residential buildings

• mid-1998 construction of a 129 room Marriott Residence Inn at the southern end of the Boulevard

ren3.JPG (20975 bytes)• mid-1999 construction of a 150 room Marroitt Fairfield Inn at the southern end of Ocean Avenue

 